Scope: Fleet (site aggregate)

State-of-Health — Recorded & Projected

Solid = recorded · dashed = projection · shaded = p5–p95 · amber = recorded-duty baseline · red = 80% EOL

Operating Duty Scenario

By default the projection continues the asset's recently observed duty — switch the window or adjust the levers to explore lighter/heavier operation. Lower stress → slower fade → longer life.

Operating Duty Scenario

Project forward the duty observed over the last:
Depth of Discharge80%
Operating temperature25 °C
Daily throughput1.0/day
Projected EOLFeb 2047
Remaining useful life20.6 yr
Fade rate0.97 %/yr
+20.6 yr vs observed duty

Warranty & End-of-Life

Terms: 10 yr or 6,000 cycles at ≥ 80% SOH · commissioned Jan 2025

Current SOH100%
Projected EOLFeb 2047at 80% SOH
Remaining life20.6 yr
Fade rate0.97 %/yr
Warranty statusHealthy

Degradation Drivers

SHAP feature importance for SOH degradation model.